In week 1 we completed the roofing on the following addresses on Sandpiper – 1700-1712,1716-1728,1800-1812, 1816-1828, 1832-1844, and 1848-1860. Next week we will roof 1864-1876, 1801-1813, 1817-1833, 1837-1853 and 1857-1869 weather permitting. Painting began on Friday 2/17 at 1700 Sandpiper and will continue on Sandpiper through next week. Gutters will follow paint and we anticipate finishing gutters on units 1700-1828 by the end of next week.
Thank you for your cooperation. The first week of construction went very well. We received excellent feedback from many homeowners in the community.